Science & Technology29 July 20264 min read
Nuclear capacity stands at 8,780 MW against 100 GW target for 2047, Lok Sabha told
Union Minister of State for Atomic Energy and Space Dr. Jitendra Singh told the Lok Sabha in written replies that India has 8,780 MW of installed nuclear power capacity across 24 plants. These supplied about 3.1% of total electricity generated in 2025-26. The government's Nuclear Energy Mission for Viksit Bharat aims to take capacity to 100 GW by 2047.
Reactors under construction
Ten reactors totalling 8,000 MW are under construction. Ten reactors were under construction or commissioning in 2023-24, and three of them, totalling 2,100 MW, have since entered commercial operation: KAPP-3&4 (2 x 700 MW) at Kakrapar in Gujarat and RAPP-7 (700 MW) at Rawatbhata in Rajasthan. RAPP-7 began commercial operation on 15.04.2026. Construction of Kaiga-5&6 (2 x 700 MW) in Karnataka has begun with the first pour of concrete, after the required statutory and regulatory clearances. No new nuclear power projects were sanctioned in the last three years.
The projects of the Nuclear Power Corporation of India Limited (NPCIL) are at different stages:
- RAPP-8 (700 MW) is at 96.26% physical progress as of June 2026 and is expected to be operational in 2026.
- Kudankulam 3&4 (2 x 1,000 MW) is at 82.65%, with commissioning expected in June 2027 and June 2028. Kudankulam 5&6 is at 45%, expected in June 2029 and March 2030.
- Gorakhpur 1&2 in Haryana (2 x 700 MW) is expected to take about six years from first pour of concrete, which will start after ground improvement works of the Nuclear Island are completed. Its cost of ₹20,594 crore is under revision.
- Kaiga-5&6 is expected in June 2031 and June 2032, at a cost of ₹21,000 crore that is also under revision.
Separately, BHAVINI is commissioning the 500 MW Prototype Fast Breeder Reactor (PFBR) at Kalpakkam, Tamil Nadu, at an estimated completion cost of ₹8,181 crore. Full commissioning is expected by March 2027.
The roadmap to 100 GW
The government cited energy security, clean energy generation and net-zero targets for the mission. The 8.78 GW now installed is expected to reach about 22 GW by 2031-32. Another 32 GW is envisaged under NPCIL beyond 2032, made up of indigenous Pressurised Heavy Water Reactors (PHWRs) and Light Water Reactors (LWRs). The government has approved pre-project activities for two 500 MW fast breeder reactors, FBR-1&2, at Kalpakkam, to the same design as the PFBR.
The remaining 45 GW, of different reactor technologies, is expected from other central and state public sector enterprises, the private sector and joint ventures under different business models. The government has also announced measures to enable research and development in Small Modular Reactors (SMRs) and other advanced technologies.
The enabling law
The Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Act, 2025 allows wider participation in the sector by public and private entities, including industries and research institutions. Once rules are framed under the Act, states, industries and research institutions can collaborate with the government. The reply also said NPCIL entered into agreements and collaborations in the last three years to augment nuclear generation.
Safety and waste arrangements
The government said safety gets the highest priority at every stage from siting to operation. Plants follow redundancy, diversity and fail-safe principles, with an overlapping defence-in-depth approach under codes and guides of the Atomic Energy Regulatory Board (AERB), which monitors safety through multi-level reviews. Emergency plans approved by the regulator are in place at every plant site before operations begin, and periodic exercises test response and inter-agency coordination.
Radioactive waste is governed by the Atomic Energy (Safe Disposal of Radioactive Wastes) Rules, 1987. These require every waste-generating facility to hold an AERB authorisation to discharge effluents, with limits based on international norms. Gaseous, liquid and solid waste are each treated by methods suited to their nature. High-level waste from reprocessing spent fuel is vitrified and stored in a Solid Storage Surveillance Facility, consistent with International Atomic Energy Agency (IAEA) guidelines.
The Department of Atomic Energy (DAE) said it follows a closed fuel cycle, treating domestic spent fuel as a resource and reprocessing its useful components as fuel for future reactors. Partitioning separates long-lived radioisotopes before vitrification and allows recovery of isotopes such as Cesium-137, Ruthenium-106 and Strontium-90 for healthcare uses. The DAE said this reduces the waste to be stored and removes the need for a deep geological repository in the near future.