Science & Technology6 August 20265 min read
Jitendra Singh tells Rajya Sabha first uncrewed Gaganyaan flight is targeted for Q4 2026
Minister of State for Space Jitendra Singh told the Rajya Sabha that Gaganyaan, India's first human spaceflight mission, has reached major milestones in developing and validating its human-rating systems. The first uncrewed mission, carrying the Vyommitra half-humanoid, is targeted for the fourth quarter of 2026.
In written and oral replies, he also gave the timeline for the Bharatiya Antariksh Station, the commercial launch record of the LVM3 rocket, support for private industry and ISRO's work in Jammu & Kashmir.
Where Gaganyaan's testing stands
The Human Rated Launch Vehicle (HLVM3) has completed development and ground testing of all its propulsion stages and structures. Propulsion systems of the Crew Module and Service Module have been developed, tested and qualified. Engineering models of the Environmental Control and Life Support System, Thermal Protection System, Deceleration System, Crew Module Up-righting System and end-to-end avionics have also been developed and tested.
All five types of motors for the Crew Escape System (CES) have been developed and successfully static tested, and the associated structures realised and qualified. The TV-D1 Test Vehicle Mission, which validated the Crew Escape System in flight, has been completed. Integrated Air Drop Test-01 and Test-02, using a simulated Crew Module, validated the deceleration system. Activities for the next Test Vehicle Mission, TV-D2, are in progress.
The ground communication network has been finalised, IDRSS-1 feeder stations and terrestrial links established, recovery assets identified and the crew recovery plan worked out. Mission infrastructure includes the Orbital Module Preparation Facility, Gaganyaan Control Centre, Crew Training Facility and modifications to the Second Launch Pad.
The first uncrewed experimental mission is meant to validate technologies being developed for the first time under the programme. Two more uncrewed missions, in the configuration of the first crewed flight, are targeted by 2027, before India's maiden human orbital mission.
Space station and international partners
The Bharatiya Antariksh Station is planned to be operational by 2035. ISRO has worked out a five-module configuration, and the Government has approved development and launch of the first module, BAS-01. In September 2024 the Union Cabinet approved ₹20,193 crore for eight missions under the Human Spaceflight Programme.
ISRO works with the European Space Agency on network operations support and with the Australian Space Agency on recovery of the crew and crew module. France's CNES helps train flight surgeons and ground support teams, while Russia's Roscosmos is involved in astronaut training and procurement of critical human spaceflight systems.
Launch market and private industry
The LVM3-M6 mission placed US-based AST SpaceMobile's BlueBird Block-2 communication satellite in a 520 km circular Low Earth Orbit. At 6,100 kg, it is the heaviest payload LVM3 has launched from Indian soil. The Minister said the launch demonstrated India's technological prowess and raised commercial confidence in LVM3, making it one of the preferred vehicles in the international commercial launch market.
He said international cooperation is pursued for strategic and technological gains, with meeting Space Vision 2047 targets, including human spaceflight, a space station and exploration missions, as its core. The strategy includes enhancing launch capability, widening the ground station network, promoting Indian industry at international exhibitions and business forums, and integrating it into global supply chains. The Government is also enabling the private sector through IN-SPACe to build indigenous capabilities, including launch vehicles.
IN-SPACe schemes are PAN India, so State-wise and gender-wise details are not maintained. The Minister said the private space sector is in a nascent phase, so interventions focus on baseline infrastructure, technology transfer, technology development and investment. IN-SPACe promotes its schemes through industry meetings, Space technology Adoption and Awareness Workshops (SAAW), webinars, stakeholder consultations, conferences and exhibitions.
ISRO applications in Jammu & Kashmir
Over the last five years, ISRO and the Department of Space have implemented satellite applications in the Union Territory. Twelve operational communication satellites cover it, with capacity offered to service providers for telecom and broadband.
Funded projects include Land Cover Land Use mapping (2025-28, ₹75.78 lakh sanctioned), SILAAS (2023-28, ₹50.16 lakh) and monitoring under WDC-PMKSY 2.0 (2023-29, ₹4.95 lakh). Completed projects include Space based Information Support for Decentralised Planning - Update (2019-24, ₹220 lakh), IWMP watershed monitoring (2022-23, ₹27.62 lakh), the National Wetland Inventory and Assessment (2018-22, ₹11.43 lakh) and a desertification and land degradation study (2017-21, ₹5.91 lakh).
ISRO is working on experimental landslide forecasting for all districts of the UT under the Satellite Integrated Landslide Assessment and Alert System (SILAAS). It also runs workshops and training for disaster management organisations, including regional training on the National Database for Emergency Management, which J&K participants attended.
ISRO has set up the Satish Dhawan Centre for Space Science at Central University of Jammu, giving faculty and research students access to ISRO facilities. Tele-education reaches the UT through satellites under PM e-Vidya, telemedicine nodes are installed, and the High Throughput Satellite GSAT-N2 was added in 2024 to enhance broadband connectivity.