The Union Cabinet, chaired by Prime Minister Narendra Modi, approved GOBARdhan, the National Circular Bioenergy Scheme, on 6 August 2026, with a total outlay of ₹23,731 crore. The scheme will run from FY 2026-27 to FY 2035-36 and will be administered by the Ministry of Petroleum and Natural Gas (MoPNG). It aims to establish Compressed Biogas (CBG) as a major part of India's future energy mix and to raise domestic CBG production nearly ten-fold.
Why the scheme was needed
India meets nearly 50 per cent of its natural gas requirement through imports. The Strait of Hormuz, where disruptions have been reported, carries nearly 55 to 60 per cent of India's LNG imports. The government cites this as a reason to strengthen domestic energy production.
GOBARdhan (Galvanizing Organic Bio-Agro Resources Dhan) began in 2018 under the Swachh Bharat Mission (Grameen) as part of solid and liquid waste management. It converted animal waste, kitchen leftovers, crop residue and market waste into biogas and bio-slurry.
The CBG ecosystem was until now spread across four ministries. It is now consolidated under MoPNG as the nodal ministry, with the aim of a unified approach to policy and implementation, and greater certainty for investors, lenders and developers.
The earlier building blocks were the Sustainable Alternative Towards Affordable Transportation (SATAT) initiative, the Biomass Aggregation Machinery (BAM) Scheme, the Development of Pipeline Infrastructure (DPI) Scheme, the Market Development Assistance (MDA) Scheme for organic manure, and Central Financial Assistance (CFA) for CBG plants under the National Bioenergy Programme. These helped commission over 200 CBG plants.
The six components
The first is assured offtake. City Gas Distribution (CGD) entities will procure CBG to meet the notified CBG Obligation for City Gas Distribution entities: 3% in FY 2026-27, 4% in FY 2027-28 and 5% from FY 2028-29 onwards, in the CNG (Transport) and PNG (Domestic) segments. The government says this turns the blending obligation into a long-term demand signal.
The second is price. A government-backed administered price of Rs 2,110 per MMBTU, equivalent to ₹105 per kg of CBG, will apply over a minimum ten-year horizon. Consumer affordability is to be protected through government support and a market-based cost-sharing mechanism.
The third is capital assistance of up to ₹2 crore per ton per day (TPD) of installed capacity for eligible greenfield projects. Support extends to value-chain assets for feedstock aggregation and organic manure processing, as well as plant machinery. Brownfield projects expanding capacity are also eligible.
The fourth is support for cluster-based and standalone pipelines linking CBG plants to trunk pipelines and CGD networks, to reduce evacuation costs.
The fifth is a Credit Guarantee Mechanism covering up to 85 per cent of eligible loans for MSME-based CBG projects. It is meant to lower collateral requirements and widen participation by MSMEs, women entrepreneurs and first-time developers.
The sixth is a CBG Ecosystem Challenge Fund for district-level implementation. It will support feedstock mapping, aggregation infrastructure, district CBG planning, technology adoption, value addition of organic manure and capacity building.
Expected benefits
CBG is chemically equivalent to natural gas and can be integrated into the existing gas ecosystem. Each plant also creates a local circular economy in feedstock supply, transport, plant operations and organic manure, while supporting waste management and lower emissions.
Over a decade, the government projects forex savings of over ₹40,000 crore, displacement of 10 MMT of fossil fuel, more than ₹75,000 crore added to GDP, over 1.5 lakh jobs, a reduction of more than 40 MT of CO2 emissions and 250 MMT of organic fertiliser.
Where the sector stands
Operators and planners of CBG or Bio-CNG plants can obtain a registration number through the GOBARdhan Unified Registration Portal, which is required to avail MoPNG benefits. As on 6 August 2026, 1,908 plants were registered. Of these, 217 are commissioned and produce 0.4 million standard cubic metres per day (MMSCMD), and 339 are under construction.