Government prepares PM-KUSUM 2.0 after 2.5 million solar pumps, amid groundwater concerns
PM-KUSUM, the Ministry of New and Renewable Energy's (MNRE) agricultural solar scheme, has subsidised the installation of over 2.5 million solar pumps in five years, and the government is now preparing PM-KUSUM 2.0. The central debate is how to advance clean energy in agriculture without worsening the over-exploitation of groundwater, since solar power makes pumping nearly free.
Where the scheme stands
PM-KUSUM (Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyan) was launched in 2019 and scaled up in 2024. It initially targeted 34,800 MW of solar capacity by March 2026, supported by Central Financial Assistance. The completion deadline has since been extended to 31 March 2027.
Component A covers 10,000 MW of decentralised, grid-connected solar plants. Farmers can sell power to DISCOMs at a feed-in tariff determined by the State Electricity Regulatory Commission. Component B aims to install 14 lakh standalone off-grid solar pumps to replace diesel pumps. Component C covers solarisation of 35 lakh grid-connected pumps, through Individual Pump Solarisation and Feeder Level Solarisation.
For Components B and C, the Centre pays 30% and the state at least 30%. The farmer bears the remaining 40%, of which up to 30% can be financed through bank loans. In the North-East, hill states and island Union Territories, the central share rises to 50%. The Reserve Bank of India has included the scheme under Priority Sector Lending.
As of August 2026, nearly 11.49 lakh off-grid pumps had been installed and over 15.89 lakh pumps covered through feeder-level solarisation. About 1,726 MW of decentralised capacity had been commissioned, and over 21.77 lakh farmers had benefited. Of the 25 lakh pumps installed or solarised, nearly 13.93 lakh were completed in FY 2025-26. Maharashtra set a Guinness World Record by installing 49,500 pumps in a single month.
Why the scheme matters
Agricultural electricity subsidies cost states over ₹1 lakh crore a year. The scheme reduces this outflow and eases the strain on DISCOMs. In Gujarat, subsidies covered nearly 25% of government investment within two years.
The scheme is estimated to cut diesel use by 1.38 billion litres a year. Domestically made cells and modules are mandated under Components B and C, creating assured demand of over 20 GW. Groundwater irrigation in India generates an estimated 45 to 62 million tonnes of carbon dioxide a year. In Gujarat, a single grid-connected farmer offsets about 12.3 tonnes of CO2 annually.
Concerns over water and equity
Solar pumps remove running costs such as diesel or electricity bills. With off-grid pumps, unused electricity is wasted, which encourages a "use it or lose it" response. Since an extra litre costs nothing, farmers may over-irrigate or pump water to sell to neighbours, threatening stressed aquifers in North-Western and Southern India.
Under Component C, the main incentive to conserve is selling surplus power to the grid. Financially distressed DISCOMs have been reluctant to offer attractive feed-in tariffs or procure this power, which weakens that incentive and leaves off-grid pumping as the default.
Subsidies are also frequently distributed without being mapped against Central Ground Water Board (CGWB) assessments, so high-capacity pumps reach "over-exploited" or "critical" blocks. Minimum Support Price and state procurement favour water-intensive crops such as paddy and sugarcane, even in semi-arid regions. The 40% upfront share remains prohibitive for small and marginal farmers, skewing adoption towards wealthier ones. Component A requires plants within 5 km of a sub-station, which excludes remote areas lacking such infrastructure.
Proposals for PM-KUSUM 2.0 respond to these gaps.
For feeder-level solarisation, states are urged to adopt water-saving credits. Farmers consuming electricity below a scientifically determined baseline would receive direct benefit transfers, modelled on Punjab's 'Pani Bachao, Paisa Kamao' initiative.
The MNRE and the Ministry of Jal Shakti are urged to integrate their databases so that subsidies follow CGWB assessments. High-horsepower standalone pumps would be restricted in "dark zones" or over-exploited blocks. Off-grid pumps would remain the priority in energy-starved but water-abundant Eastern India, while grid integration would be the focus in Punjab and Haryana.
Pump deployment, especially under Component B in vulnerable zones, would be made contingent on drip and sprinkler systems under the Per Drop More Crop initiative. MSP and procurement would shift farmers from paddy and sugarcane towards millets, pulses and oilseeds. In fragmented or irrigation-deprived areas, deployment would run through Water-User Associations, Farmer Producer Organizations and rural water-selling cooperatives instead of individual ownership.