Haroli bulk drug park in Una still mostly at tender stage, Centre tells Rajya Sabha
Minister of State for Chemicals and Fertilizers Anupriya Patel told the Rajya Sabha in a written reply that central assistance to pharmaceutical units in Himachal Pradesh under the Strengthening of Pharmaceuticals Industry (SPI) scheme is only partly disbursed, and that the Haroli bulk drug park in Una is still mostly at tender stage. She said the grant of Environmental Clearance, on 25.09.2025, was among the main causes of delay.
What the SPI sub-schemes have delivered
SPI is a Central Sector Scheme. Under its sub-scheme Assistance to Pharmaceutical Industry for Common Facilities (APICF), which supports common infrastructure in existing pharmaceutical clusters, two Solan projects have been approved.
The first is Welzo Research & Development Private Limited, approved in FY 2022-23 with grant-in-aid of ₹19.53 crore for a research and development and testing laboratory. The project is complete. The Centre released ₹5.86 crore in FY 2022-23, ₹4.88 crore in FY 2023-24, ₹6.84 crore in FY 2024-25 and ₹1.95 crore in FY 2025-26.
The second is Himachal Pradesh Testing Lab Limited (HPTLL), approved in FY 2025-26 with ₹17.87 crore for a Common Facility Centre for research and development and a centre of excellence for skill development. Nothing has been released because HPTLL has not yet met the sub-scheme's procedural requirements. No Himachal proposal is pending under APICF.
The Revamped Pharmaceutical Technology Upgradation Assistance Scheme (RPTUAS) helps existing units upgrade technology and processes to Revised Schedule-M and WHO-GMP (World Health Organization - Good Manufacturing Practices) certification. In Solan, 16 units (sanctioned ₹17.19 crore) were approved in FY 2024-25 and 27 units (sanctioned ₹29.02 crore) in FY 2025-26. Incentive of ₹6.42 crore has been released to seven units.
A total of 21 applications from Himachal units are pending under RPTUAS. The minister said a temporary restriction applies until the Expenditure Finance Committee/Standing Finance Committee decides on extending the sub-scheme.
Funding and status of the Haroli park
Under the Promotion of Bulk Drug Parks scheme, the Department of Pharmaceuticals (DoP) sanctioned ₹1,000 crore on 11.10.2022 for the park at Haroli. Of this, ₹225 crore was released on 20.02.2023. The state government sanctioned ₹118.46 crore for common infrastructure facilities and released ₹35.53 crore as its share in FY 2022-23.
The facilities under implementation include a Common Effluent Treatment Plant (CETP) with Zero Liquid Discharge (ZLD), water supply, power infrastructure, steam generation, a warehouse and a centre of excellence. A solvent recovery system, an emergency response centre and solid waste management facilities are also planned.
Only a few components have physical progress:
- Raw, potable and demineralised water (approved cost ₹141.95 crore): 60% of work complete, with ₹55.6 crore spent.
- Storm water drain network (₹86.71 crore): 12% complete, with ₹9.68 crore spent.
- Internal road network and compound wall (₹149.44 crore): 10% complete, with ₹15.03 crore spent.
Tenders have been released for the CETP and solid waste management (₹49.73 crore) and for steam generation and distribution (₹312.30 crore). Tenders are still being prepared for the rest, including the warehouse (₹60.71 crore), the centre of excellence (₹110.29 crore), the internal power distribution network (₹65 crore, on which ₹14.26 crore has been spent), the incinerator, the landfill site, solvent storage and recovery, and the testing, emergency response and safety audit centres.
Why the park is behind and what happens next
The minister named three primary causes of delay: the grant of Environmental Clearance, procedural requirements for permission to fell trees, and bids for procurement. She said project activity has gained momentum since the clearance, with several infrastructure packages under implementation or at advanced stages of procurement.
The scheme's tenure has been extended to FY2026-27, based on representations from the state governments concerned, project status, fund utilisation and the expected completion of projects in that year.
Progress is reviewed regularly by the Scheme Steering Committee of the bulk drug park scheme, by the Secretary and Joint Secretary in the DoP, and by a High Powered Committee headed by Himachal Pradesh's Minister of Industries. The state government and implementing agencies are monitoring execution and expediting statutory clearances, tendering and contract awards for critical infrastructure.