Economy20 October 20264 min read
CEA maps 345.38 GW of pumped storage potential as India eases approvals
The Central Electricity Authority (CEA) has identified 345.38 GW of pumped storage potential across 320 projects and projects 100.81 GW of capacity additions between 2025-26 and 2035-36. That would take cumulative capacity to about 105.56 GW. The push to speed up Pumped Storage Projects (PSPs) is tied to India's clean energy transition.
How pumped storage works
Surplus electricity, mainly from solar and wind, is used to pump water from a lower reservoir to an upper one. At peak demand, or when renewable output is low, the stored water flows back through turbines to generate power. The water is circulated repeatedly between the two reservoirs, which is how PSPs address the intermittency of solar and wind energy.
Battery Energy Storage Systems (BESS) do a different job. They give rapid-response, short-duration storage, support frequency regulation, peak demand management and grid balancing, and can be deployed quickly near generation or consumption centres. PSPs offer long-duration, high-capacity storage and a long operational life, but need suitable geography and longer development timelines.
Projects are of two broad kinds. In on-stream projects, both reservoirs are on a river, stream or nallah. In off-stream projects, at least one reservoir is away from rivers or perennial streams. Off-stream closed-loop systems have both reservoirs away from perennial natural watercourses. Off-stream projects are being explored for faster execution and, depending on the site, possibly lower impact on aquatic ecology.
Where India stands
As of August 2026, 7.43 GW is operational across 10 PSPs. Another 15.87 GW across 11 projects is under construction or implementation, and 10.40 GW across 8 projects has been concurred or appraised by the CEA.
The identified potential comprises 56.67 GW from 62 on-stream projects and 288.71 GW from 258 off-stream projects. The Western Region leads with 129.72 GW, followed by the Southern (97.76 GW), Eastern (53.41 GW), Northern (50.32 GW) and North Eastern (14.18 GW) regions. Maharashtra has the highest state-level potential at 67.36 GW.
The CEA projects a need for 73.93 GW of energy storage capacity by 2031-32, of which 26.69 GW would come from PSPs and 47.24 GW from BESS.
According to the International Renewable Energy Agency (IRENA), global pumped storage capacity reached 159.8 GW at the end of 2025, led by China (66 GW), Japan (22 GW) and the US (19 GW). India ranked fourth with 7.18 GW.
What has changed for developers
The Ministry of Power notified the Guidelines to Promote Development of Pumped Storage Projects in April 2023 to facilitate faster development. The government also provides budgetary support for roads, bridges, railway sidings, ropeways, communication facilities and transmission lines to improve project viability.
The Tariff-Based Competitive Bidding Guidelines, 2025 set out a transparent framework for procuring PSP storage capacity and stored energy. PSPs awarded for construction by 30 June 2028 are eligible for a 100% Inter-State Transmission System (ISTS) charge waiver for 25 years from commercial operation.
On approvals, revised CEA guidelines cut the timeline for concurrence of Detailed Project Reports from 90 to 50 days and removed the requirement for clearance of inter-state aspects. In August 2025, the capital expenditure threshold requiring CEA concurrence for hydroelectric projects was revised to ₹3,000 crore, while off-stream closed-loop PSPs were exempted irrespective of project cost.
The Ministry of Environment, Forest and Climate Change (MoEFCC) has introduced a Category B2 classification for eligible PSPs, subject to applicable conditions. It has also reduced baseline data requirements for off-stream projects and revised forest survey and borehole exploration provisions. The CEA's Jal Vidyut DPR portal allows real-time monitoring of surveys and investigations.
National electricity planning also integrates energy storage with transmission development, to help renewable integration, reduce grid congestion and improve reliability. India's target is 500 GW of non-fossil fuel capacity by 2030.