Economy15 July 20263 min read
CCEA approves two Varanasi elevated corridors costing over ₹25,400 crore under HAM
The Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi, has approved two elevated corridor projects to decongest Varanasi in Uttar Pradesh. Both will be implemented under the Hybrid Annuity Model (HAM) and are aligned with the PM Gati Shakti National Master Plan.
The Ganga Elevated Corridor (NH-19 to Ring Road) is 46.039 km long and links National Highway-19 with the Varanasi Ring Road (NH-135B). Its total capital cost is ₹14,447.64 crore. The Varuna Riverbank Elevated Corridor (NH-31 to Ring Road) is 43.218 km long and links NH-31 with the Ring Road. It will cost ₹10,998.32 crore.
What the Ganga corridor includes
The corridor is a link route with riverbank connectivity along the Ganga. It has a six-lane elevated main carriageway, loops, ramps, link roads and service roads. The cost includes civil construction of ₹6,037.85 crore (with utility shifting, excluding GST) and land acquisition of ₹541.11 crore under NH(O).
The main structures are:
- a 910 m cable-stayed bridge across the Ganga;
- a 1.32 km extradosed Foot Over Bridge-cum-Major Bridge, with travelators giving pedestrians access to the Kashi Vishwanath Temple;
- a Rail Over Bridge over the existing or proposed Malviya Bridge;
- an elevated spur between BHU/Lanka and Samne Ghat, to ease Lanka Junction by separating through traffic from local movements.
The design also provides emergency parking bays, noise barriers, facade lighting and architectural elements inspired by Varanasi's cultural heritage.
The corridor is meant to be a high-speed, access-controlled connection between NH-19, the Ring Road, Ramnagar, BHU and other urban destinations. It would take through traffic off NH-19, the BHU-Ramnagar Corridor and NH-35, away from the densely developed urban core. Varanasi receives more than 15 crore tourists and pilgrims a year, and the corridor would improve access to the Kashi Vishwanath Temple, BHU, Namo Ghat, Ramnagar Fort, the ghats and Kashi Railway Station.
What the Varuna corridor includes
The Varuna corridor is a 6/4-lane, predominantly elevated road with a main carriageway, flyovers, loops, ramps and service roads. The National Highways Authority of India (NHAI) will execute it under HAM. Civil construction is costed at ₹4,565.33 crore and land acquisition at ₹934.91 crore.
It is described as a major component of the Varanasi Decongestion Plan. It is to link NH-31 with Kashi Railway Station and improve access to the Ring Road, Varanasi Airport, the city's railway stations, Ramnagar Port, Sampurnanand Sanskrit University, the ghats and the adjoining Chandauli region.
Speed, travel time and multimodal links
Both corridors are designed for an operating speed of 80-100 km/h. For the Ganga project, average travel time across its influence area is expected to fall from about 60 minutes to 20 minutes, a cut of nearly 67 per cent. Travel from NH-19 to Kashi Railway Station is expected to drop from about 50 minutes to about 25 minutes. On the Varuna corridor, the NH-31 to Kashi Railway Station trip is expected to fall from about 40 minutes to 20 minutes.
Under the PM Gati Shakti framework, each corridor links one Economic Node, the Chandauli SEZ, and one Social Node, the Chandauli Aspirational District. Each also links six major Logistics Nodes: Lal Bahadur Shastri Airport, Kashi Railway Station, Banaras Railway Station, Varanasi City Railway Station, Pt. Deen Dayal Upadhyay Junction and Ramnagar IWAI Port.
The stated benefits are better logistics efficiency, road safety, lower vehicle operating costs, and faster, uninterrupted passenger and freight movement. The corridors are also expected to ease the movement of agricultural produce, industrial goods, construction materials and minerals across eastern Uttar Pradesh.