Cabinet approves Green Energy Corridor Phase-III with ₹1,86,405 crore outlay
The Union Cabinet has approved Green Energy Corridor Phase-III (GEC-III), with an outlay of ₹1,86,405 crore, to strengthen the Intra-State Transmission System (InSTS) and evacuate up to 135 GW of renewable energy. The scheme is to be fully commissioned and operational by FY 2032-33.
The outlay has two parts: ₹1,36,378 crore for developing the InSTS and ₹50,000 crore for 50 GWh of Battery Energy Storage Systems (BESS). It also includes Central Financial Support of ₹54,082 crore, which will help offset intra-state transmission charges and keep power costs down for end users.
How the scheme will work
GEC-III is exclusively intra-state. It aims to connect renewable-rich zones directly with regional load centres within States and Union Territories. The BESS capacity will be deployed at the renewable energy developer or generator end, or at other locations important for grid flexibility. The batteries are meant to address intermittency, congestion and peak-hour curtailment, and to help meet demand during non-solar hours.
All greenfield projects under the InSTS component will be built through Tariff Based Competitive Bidding (TBCB). Brownfield upgrades and network strengthening will be done on a Cost Plus Basis. State Transmission Utilities will be the overall implementing agency, working with public and private Transmission Service Providers, who will take part under TBCB on a Build-Own-Operate-Maintain model.
What the earlier phases covered
The Green Energy Corridor is implemented by the Ministry of New and Renewable Energy. It stems from a 2012 study by Power Grid Corporation of India Limited and was launched in 2015 to upgrade grids that could not handle the erratic, geographically dispersed nature of large-scale renewable generation. It covers both inter-state and intra-state networks, along with Renewable Energy Management Centres, which use real-time data and forecasting to balance solar and wind output, as well as reactive power compensation and energy storage.
Phase-I covers eight states: Tamil Nadu, Rajasthan, Karnataka, Andhra Pradesh, Maharashtra, Gujarat, Himachal Pradesh and Madhya Pradesh. It aims to integrate 24 GW of renewable energy through 9,700 circuit kilometres (ckm) of lines and 22,600 MVA of substation capacity, with completion targeted by FY 2027. According to government data, 9,130 ckm had been built as of June 30 against a target of 9,461 ckm. A parliamentary panel has previously flagged delays.
Phase-II covers seven states: Gujarat, Himachal Pradesh, Karnataka, Kerala, Rajasthan, Tamil Nadu and Uttar Pradesh. It envisages 10,750 ckm of lines and 27,500 MVA of substation capacity to evacuate around 20 GW over 2021-22 to 2025-26, with Central Financial Assistance to reduce transmission charges.
Expected benefits
The scheme is meant to support the expanded target of 900 GW of installed non-fossil capacity by 2035. It is expected to ease bottlenecks at state borders and allow power from distant solar and wind sources to flow to local distribution grids. Central assistance reduces the capital cost of State Transmission Utilities, which is expected to lead to lower retail tariffs.
The BOOM model under TBCB is expected to bring transparency, cost optimisation and innovation. Construction of lines, substations and BESS complexes is expected to create direct and indirect jobs, and the scheme is also meant to drive domestic battery manufacturing and grid management capabilities.
Risks to delivery
Administrative delays and local reluctance to build lines on agricultural and forest land risk cost and time overruns. State distribution companies may delay payments to Transmission Service Providers even with Central subsidies. Supply chains for lithium, cobalt and specialised power equipment are exposed to international disruptions. Integrating large volumes of intermittent power also needs smart-grid technologies, advanced forecasting and dispatch systems, and skilled workers.
The scheme's success is said to depend on timely implementation, land management, reform of State utilities, local supply-chain capabilities, technology readiness and Centre-State coordination.