Economy27 July 20265 min read
Coal Ministry tells Rajya Sabha it targets 100 MT gasification capacity by 2030
The Ministry of Coal has told the Rajya Sabha that the National Coal Gasification Mission targets 100 Million Tonnes (MT) of gasification capacity by 2030, and that coal imports by thermal power plants fell about 27.4% in FY 2025-26. Minister of State for Coal and Mines Satish Chandra Dubey gave the information in written replies. The Ministry also said it has notified the Coal Exchange Rules, 2026.
The replies describe three tracks to reduce import dependence: gasification of domestic coal, better logistics and pricing for domestic supply, and a regulated exchange for trading coal.
Gasification pipeline and support
About 22.6 Million Tonnes Per Annum (MTPA) of gasification capacity is operational or under implementation. Jindal Steel Limited (JSL) accounts for about 8 MTPA, which is operational. Talcher Fertilisers Limited has about 2.6 MTPA under implementation. Eight projects under the ₹8,500 crore Financial Incentive Scheme of 24.01.2024 add about 12 MTPA, also under implementation.
On 13.05.2026 the Government approved a ₹37,500 crore Scheme for Promotion of Surface Coal/Lignite Gasification Projects. The Ministry said it is expected to use about 75 MTPA of coal and contribute substantially to the 100 MT target.
Under the ₹8,500 crore scheme, one JSL project has achieved financial closure and is under construction. Five projects overall have completed ground breaking and are at various stages of clearances or implementation.
The support package has several parts:
- A capex incentive of 15% under the ₹8,500 crore scheme, and up to 20% of eligible plant and machinery cost under the ₹37,500 crore scheme.
- A new coal linkage sub-sector, production of Syngas leading to coal gasification, at a floor price equal to that of the power sector, with linkage tenure extended to 30 years. A project with an auctioned coal mine is eligible for linkage beyond allocated mine capacity.
- A 50% rebate in revenue share for coal used for gasification.
- A framework and guidelines for underground coal gasification (UCG), with exemption for pilot projects. The floor price for auction of UCG coal blocks has been cut to 2% from the 4% applicable to underground coal mining, and upfront payment has been waived, with a 50% rebate on Performance Bank Guarantee.
The Ministry said gasification allows cleaner, value-added use of domestic coal for synthetic natural gas, chemicals, fertilisers and hydrogen. It expects the initiatives to strengthen energy security, promote import substitution and attract investment. Once projects under the two schemes and Talcher Fertilisers are commissioned, import substitution is estimated at about ₹1.5 lakh crore annually.
Why imports fell
Coal imported by thermal power plants was 45.4 MT in FY 2025-26, against 62.5 MT in FY 2024-25. Imports by plants designed on imported coal were 2.88 MT in April 2026, against 3.97 MT in April 2025, a fall of around 27.45%.
The Ministry pointed to the Integrated Coal Logistics Plan, which includes 33 critical railway projects, expansion of First Mile Connectivity infrastructure, more rail evacuation capacity with the Ministry of Railways, and multimodal transport via rail, coastal shipping and inland waterways. It said 139 First Mile Connectivity projects with 1319 MT capacity are planned by FY 2029-30, and coal PSUs are implementing eight railway projects in coal-bearing States.
It also cited the removal of the GST compensation cess, which it said has made domestic coal competitive against imported coal. Over eight years, the notified price of most Coal India Limited (CIL) grades has risen by only ₹20 per tonne. In 2026 (till June), CIL held three tranches of Short-term Auctions and one tranche of Long/Medium Term Auction under Window-II of the Revised SHAKTI Policy, 2025, allowing power plants to book coal at near zero premiums.
Coal remains under Open General License, so consumers may import from a source of their choice on paying the applicable duty. The Government has allowed Imported Coal Based plants to secure coal under the Revised SHAKTI Policy, 2025. The Ministry said its focus is raising domestic production and eliminating non-essential imports.
Coal Exchange Rules
The Ministry notified the Coal Exchange Rules, 2026 through G.S.R. 442 (E) dated 4 June 2026. They are made under Section 18B(3) of the Mines and Minerals (Development and Regulation) Act, 1957, as inserted by the MMDR Amendment Act, 2025 of 21 August 2025 (Section 18B). A notification of 10 December 2025 (S.O. 5730 (E)) appointed the Coal Controller Organization (CCO) as the Authority to register and regulate Coal Exchanges.
Any entity, including captive and commercial miners, can enter delivery-based contracts on the exchange. Bidding and price discovery will follow procedures approved by the CCO, and the final price will be adjusted for quality using the contract's price-adjustment mechanism and the coal sampling agency's certification. The Ministry said market surveillance under the Rules is meant to prevent manipulation or abuse and bring transparency. Public sector coal companies may also use the platform.